Pembangunan Crossing Saluran Jati Bunder Capai 50 Persen

Progress of Crossing Channel Construction on Jalan Jati Bunder Reaches 50 Percent

Progress of crossing channel construction on Jalan Jati Bunder, RW 14, Kebon Melati Urban Village, Tanah Abang Sub-district, Central Jakarta has reached 50 percent. It was targeted to be completed this week.

This crossing channel is built to follow up proposal from Kebon Melati Urban Village

Tanah Abang Sub-district Water Resources Task Force Head, Eli Menawan Sari conveyed, crossing channel is built along 6.5 meters with width and height of 0.6 meters. The construction has been carried out since last week.

"This crossing channel is built to follow up proposal from Kebon Melati Urban Village, moreover its existence is important to stop inundation when it rains," she conveyed, Tuesday (11/16).

Channel on Jalan Tebet Timur Dalam VIII Dredged

In this project, her side deployed 5 personnel equipped with one breaker, one generator set, two crowbars, and one club hammer.

"In the process, we are constrained by cables and pipes that cross the crossing channel. But so far, we can handle it," she mentioned.

Her side expected the crossing channel can minimize inundation when heavy rain falls.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye872 personTiyo Surya Sakti
  2. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye790 personTiyo Surya Sakti
  3. Pramono: Jakarta Government Acts Swiftly to Tackle Flooding

    access_time30-01-2026 remove_red_eye374 personDessy Suciati
  4. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye371 personAldi Geri Lumban Tobing
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye363 personDessy Suciati
close